In 2018
The project includes three storage ponds and their associated pipeline systems, with a total catchment area of 235.87ha. Among them, the 1# storage tank, with a design volume of 8064m³, has successfully applied water quality online treatment facilities, with a capacity of 4m³/s. In the selection of this project's plan, Guhong becomes the highest rated plan design unit, providing the main design and framework for this project.
Functional equipment such as gate type flushing system, hydraulic particle separator, electrical flow regulator, and flat fine grid are installed in the storage tank and interception well. By collecting and treating combined sewer overflow sewage, it can effectively reduce the pollution caused by combined sewer overflow on rivers and frequency of overflow, improve the living environment of residents, and accelerate the development of sponge cities.